Care Home Solar Install Timeline 2026 — 12-20 Week Process

Realistic 12-20 week timeline for UK care home solar installs in 2026 — feasibility, survey, DNO, install, commissioning, with what each phase actually involves.

Published 15 May 2026 by SEO Dons Editorial

“How long does this take?” is one of the first questions every care home operator asks when considering solar. The honest answer is 12-20 weeks from signed quote to commissioning for most installs — but understanding what happens in each phase helps you plan around residents, staff, and the home’s operational rhythm. This piece breaks down the typical UK care home solar install timeline, week-by-week.

The longest delay in most programmes is not the installation but consent: a prior approval application for an array above 50 kW has to be decided before work starts. Our guide to planning permission for solar panels on care homes sets out when it applies.

The 5-phase timeline

A typical 50 kWp install on a 50-bed UK care home runs across five phases:

PhaseDurationWhat happens
1. Desk feasibility5-7 working daysHalf-hourly meter data analysis + roof photo review
2. Site survey + design2-3 weeksStructural and electrical engineer visit
3. DNO G99 application4-12 weeksParallel-tracked with install prep
4. Mobilisation + install1-3 weeks on siteScheduled around mealtimes and visiting hours
5. Commissioning + handover1 weekLive generation display setup, staff briefing

Total: 12-20 weeks from signed quote to commissioning.

For listed buildings (around 8% of UK care home stock), add 12-16 weeks for Listed Building Consent. For sites with asbestos survey requirements (pre-1980 conversions), add 2-4 weeks.

Phase 1 — Desk feasibility (week 0-1)

  • Half-hourly meter data — your electricity supplier provides this on request. 12 months of half-hourly consumption data lets the installer model self-consumption rates accurately against modelled solar generation.
  • Roof photo or satellite image — gives the installer roof orientation, pitch, shading, accessibility at a glance.
  • System sizing model — typically PVSyst or industry-standard equivalent, modelling annual generation against your demand profile. Includes system spec, year-1 generation, year-1 saving, 25-year cashflow, all funding routes modelled.

You commit to nothing at this stage.

Phase 2 — Site survey + design (week 1-4)

Once you accept an installer’s indicative proposal, the installer’s structural and electrical engineers usually survey the site. A typical survey takes 90-120 minutes and covers:

  • Roof condition assessment — remaining life, condition of tiles/slates/membrane, structural integrity
  • Asbestos survey (mandatory under HSE CAR 2012 for pre-1980 stock) — typically £300-£800
  • Structural loading assessment — heat pump and solar plant loading on the existing structure
  • Electrical infrastructure — existing consumer unit position, DNO incoming supply, single-phase vs three-phase
  • Plant room location — for inverters and (where specified) battery storage
  • Access routes — scaffolding, cable runs, crane positions for larger installs

Output is a final design (panel layout, inverter specification, cable routing) and a fixed-price contract. Sign-off here triggers the install programme.

Phase 3 — DNO G99 application (week 2-14)

Grid connection is the longest phase of the install programme, and largely outside the installer’s control. The G99 application is submitted to your local Distribution Network Operator (UK Power Networks, Northern Powergrid, Electricity North West, SP Energy Networks, SSEN, or National Grid ED depending on your region) shortly after contract signing.

What happens during the DNO phase:

  • Application submitted — typically week 2 of the programme
  • DNO review — DNO checks local network capacity, may request additional information
  • Acceptance notice issued — typically 4-12 weeks for sub-100 kWp systems
  • Connection agreement — final terms confirmed before commissioning

For larger installs above 200 kWp, expect 6-18 months.

DNO timing depends on the network area and on the headroom at your local substation. No network operator publishes a typical timeline for care-home-sized connections, so ask your own network operator for its estimate and check its capacity map before you size the array. In Scotland a transmission impact assessment is needed above 200 kW on the mainland and 50 kW on the islands, against 5 MW in England and Wales, which can add time to larger care-village schemes (NESO, 12 May 2025). Northern Ireland uses NIE Networks’ own G98/NI and G99/NI process.

Phase 4 — Mobilisation and install (week 8-18)

The phase that residents and families actually notice. Mobilisation typically happens once DNO acceptance is confirmed (or in parallel for sites where DNO acceptance is straightforward). Pre-mobilisation activities:

  • Care home staff briefing — 7-14 days before mobilisation. Cover access routes, contractor identification, scheduling around mealtimes and visiting hours.
  • Family notification — leaflet drop or newsletter inclusion 14-21 days before. Reassures families about disruption levels.
  • Resident notification — verbal briefing through care staff for residents who can engage; quiet acknowledgement for dementia residents.
  • Site setup — scaffolding erection (typically 1-2 days), site security, contractor toilet/welfare arrangements.

Install itself runs typically 5-15 working days for a 50 kWp system. Day-by-day:

  • Days 1-2: Scaffolding erection, site setup, panel and inverter delivery
  • Days 3-7: Panel mounting on roof, DC cable runs to inverter location
  • Days 8-10: Inverter installation in plant room, AC cabling to consumer unit, monitoring system setup
  • Days 11-12: DNO connection — typically a planned brief outage of 2-4 hours, scheduled with the registered manager around mealtimes
  • Days 13-15: Final electrical commissioning, monitoring activation, scaffolding strike

Working hours are 09:00-16:30 typically — no overnight working. Noisier operations (roof penetration, drilling) align with structured activity schedules to minimise resident disruption.

Phase 5 — Commissioning and handover (week 18-20)

The system goes live. What happens:

  • Final electrical inspection — independent NICEIC inspector signs off the installation

  • MCS certification — the installation is registered with MCS; certificate provided

  • Building insurer notification — system spec sheet sent to your broker

  • Live generation display setup — reception screen showing current generation, today’s kWh, year-to-date carbon avoided (optional, typically well-received)

  • Staff briefing — 30-minute session for care staff covering how the system works, key facts for family questions, maintenance contact details

  • CQC Well-led evidence pack — comprehensive documentation for your inspection file: system spec, MCS certificate, generation log template, carbon saving narrative, family communications template

What you should ask at each phase

Phase 2 (site survey): “Are there any hidden costs?” Asbestos, structural reinforcement, listed building, reroofing — all flagged before contract.

Phase 4 (mobilisation): “What will residents and families experience?” Detailed briefing pack, daily schedule, point of contact for any issues during install.

Phase 5 (commissioning): “How do I show this to my CQC inspector?” Complete evidence pack designed to slot into the home’s inspection file.

The honest no — when timing doesn’t work

Things no installer can accelerate: DNO acceptance timing (DNO-controlled) and Listed Building Consent (planning-authority-controlled).

For end-of-tax-year capex deadlines (March 31 for most operators), starting the conversation by November is the safe timing. Starting in February typically means commissioning in May-June rather than capturing the March year-end.

Get in touch

Get the numbers for your own care home

Send your home name, number of beds, postcode and contact details. We will review what you send and reply by email.

  • ✓ Independent guide: we do not sell or fit solar
  • ✓ We reply by email
  • ✓ Your postcode tells us which nation's planning, rates and funding rules apply

We reply by email. By submitting you agree to our privacy policy.

Continue your research

Care home solar is a multi-dimensional decision. These pages cover the questions operators ask most often:

How this site works

  • Independent specialist guidance
  • Sourced 2026 rates & grant data — key facts re-checked October 2026
  • No installer agenda, no commission bias
Costs & payback Get in touch